《道路.排污管网施工方案.doc》由会员分享,可在线阅读,更多相关《道路.排污管网施工方案.doc(67页珍藏版)》请在三一文库上搜索。
1、assessment; 2, for employees working in this sector allocation, performance evaluation and reward (or punishment recommendations) authority; 3, within the limits of responsibility according to the system of ownership of the work of the authority; 4, the right to confidentiality in the company archiv
2、es; 5, the right to the assessment of departments; 6, request other departments within the Department be reasonable coordination authority; 7, the right to review of the fees; 8, urging implementation of the personnel management system, and corresponding punishment for violations of the system recom
3、mended by the authority; Department: General Office two superiors: jobs covered by the Manager and the subordinate departments: Director, General Accounting, Treasury, material accounting, appraisal, asset manager departments job: responsible for development, audit, inspection, evaluation, managemen
4、t regulations, and the companys financial and material management. Main functions: 1, common functions, in charge of the annual, quarterly and monthly work plan and report, with regular work, looking for a job gap, improve the quality of work; 2, responsible for the companys rules and regulations, p
5、rovisions, arrangements, notices and other documents of implementation in this sector; 3, responsible for the internal management rules of construction, implementation and improvement of work; 4, in charge of the departments and agencies post functions, running processes, the development of assessme
6、nt methods and assessment work; 5, responsible for the湖南红旗市政建设股份有限公司 醴陵市体育横路改造工程投资建设人项目目 录1、施工方案与技术措施2、质量管理体系与措施3、安全管理体系与措施4、环境保护管理体系与措施5、工程进度计划与保证措施6、资源配置计划7、主要项目管理人员8、施工设备9、试验、检测仪器设备施工方案与技术措施1工程概况建设单位:醴陵市住房和城乡建设局设计单位:株洲市规划设计院本工程为醴陵市体育横路改造工程投资建设人项目。连醴陵市醴泉路和体育馆,主要内容包括原有砼路面拆除、路基处理、道路工程、排水工程、交通设施工程、路灯
7、安装工程、人行道等附属工程等,采用包工、包料、包工期、包质量、包安全、包中标综合单价、工程量按实结算原则承包。2施工部署2.1施工组织2.1.1 委派有丰富市政工程施工管理经验的优秀项目经理担任本工程项目经理,委派有同类工程施工经验的工程技术人员组成项目管理班子。作业层集中选派技术过硬、作风顽强的技术骨干,组织专业化作业队伍承接该工程施工作业。严格按ISO9002系列标准要求建立项目质量保证体系,使施工过程处于严格的受控状态。2.1.2项目经理部:设经理一名、技术负责人一名,经理部下设:工程技术部、合约部、物资设备部、安全部、综合办公室和财务部。道路、排水施工队箱涵、通道施工队绿化给水施工队土
8、石方施工队2.1.3项目管理组织机构框图(如下图)项 目 经 理项目副经理项目总工物质设备部安全保卫部财务部工程技术部质检部合约部综合办公室材料组设备组试验组施工组测量组人行道等附属工程 施工队原路面拆除、路基处理施工队稳定层浇捣施工队排水工程施工队改性沥青路面施工队交通设施施工队路灯安装工程施工队2.1.4施工班组的划分项目经理部下设七个施工队:原路面拆除、路基处理施工队,排水工程施工队、稳定层浇捣施工队,改性沥青路面层铺设施工队,路灯安装施工、交通设施施工队、人行道等附属工程施工队。2.1.5工程管理目标见表工期目标总工期:60天质量目标确保合格 安全目标杜绝死亡事故发生,年负伤率控制在0
9、.5以内。管理目标按ISO9002标准进行现场管理, 创施工现场综合考评样板工地2.2施工总体部署据工程的施工特点,对主要分项工程施工作如下总体部署:2.2.1施工区域划分以及施工顺序安排部署2.2.1.1施工区域划分分两个工作面全部展开2.2.1.2总体施工顺序施工准备测量原路面拆除、路基处理工程排水工程道路工程路灯安装工程交通设施工程人行道等附属工程2.2.1.3主要技术措施2.2.1.3.1测量由专业测量员组成的专业测量队伍,配备高精尖的测量仪器进行施工测量。(1)技术标准水准点闭合差:12L1/2mm,L为水准点间水平距,单位为km。导线方位角闭合差:40n1/2秒,n为测站数。直接丈
10、量测站允许偏差:固定测桩间距离(m)允许偏差400mm D+0.5m 且总宽度不小于0.7米。 2.4.3 管沟底的准备 对于像供水、排污或长距离输送管线的压力系统,除非设计图纸有特殊要求,一般来说,管沟底的水平精度要求并不是很高。而对于重力排水系统,坡度的等级必须达到规定的要求。 如果管沟底部相当平直,而且土壤内基本上没有大的石块,那么就没有必要再进行平整。当然,如果是一个没有受到扰动的管沟底层,那就更好。但如果管沟底已经被扰动或在开挖的过程中必须被扰动,那么其密实度至少应该达到其周围填埋材料的密实度,开挖的管沟底部一般要用直径不超过50mm 的没有尖锐棱角的小石头再混和一些沙土和粘土等材料
11、垫平。所有规格的HDPE 管道一般都可以适应少量局部的管沟底的不平坦,但如果在回填材料中含有带尖棱的石头或坚硬的页岩,那么就可能会在管道表面产生应力集中区以致损伤管道。对于在页岩及松散的岩石土壤中的开挖,为了避免与松散的岩石接触,必须为HDPE 管道提供一个均一的沟床,一般的做法是开控管沟底时应比规定的深度挖深15-20cm,然后用适当的填埋材料回填至规定高度,并夯实到95%以上。 对于支撑强度较小的湿粘土或沙土等类似的不稳定土壤,管沟的开挖的深度要比规定的值深10-15cm。然后用指定的或原开挖的材料进行回填,这样即可保证为HDPE 管提供一个均一的支撑。在不稳定的有机土壤中,如果安装地点的
12、地下水位较高以致于淹没了管道,可以在管道上增加额外的重量来抵抗管道受到的浮力,但这个额外的设计重量不应该超过基础层的支撑强度。 2.4.4管沟内管道的敷设 在管道被放入管沟之前,首先应该对管道进行外观检查,在没有发现缺陷的情况下,管道才被允许吊入或滚入管沟内。 管道通常会在地面预先连接好,有时管道可能会被预先连接成大约150 米长的许多管段,贮存在某一个地方,当需要下放及连接时,再被运到安装地点,然后采用热熔连接或机械连接的方式连接这些管段。 公称直径小于20mm 的管道可以手工拖入管沟内;对所有的大管道、管件、阀门、消防栓及配件,应该采用适当的工具仔细将它们放到管沟内;对于长距离的管道的吊装
13、,推荐采用尼龙绳索。 2.4.5 最终的管道连接与装配 管沟内管道的热熔连接同地面上管道的热熔连接方式相同,但必须保证所连接的管道在连接前必须冷却到土壤的环境温度。 HDPE 管道与金属管道、水箱或水泵相连时,一般采用法兰连接。对于HDPE管材之间,当不便于采用热熔方式连接时,也可采用法兰连接。法兰连接时,螺栓应预先均匀拧紧,待8 小时以后,再重新紧固。 2.4.6砌井2.4.6.1准备工作(1)清理基础表面复核尺寸位置和标高是否符合设计要求;(2)按设计要求选用合格机砖,并将砖湿润,但浇水要适量,否则会使墙面不清洁,灰缝不整;(3)准备砂浆,按照设计给定的砂浆配合比配料,拌制。控制好时间,使
14、砂浆拌合均匀,做到随拌随用。2.4.6.2井砌筑技术要点(1)在井坑放出检查井中心位置线,浇筑井底砼基础,按检查井半径摆出井壁砖墙位置;(2)在井基础面上,先铺砂浆后再砌砖,采用全丁24墙砌筑。采用内缝小外缝大的摆砖方法,外灰缝塞碎砖,以减少砂浆用量。每层砖上下皮竖灰缝应错开。随砌筑随检查弧形尺寸;(3)排水管管口伸入井室30mm,管顶砌砖圈加固,以减少管顶压力,拱圈高为250mm;(4)砖砌圆形检查井时,随砌随检测检查井直径尺寸。(5)排水检查井内的流槽,在井壁砌到管顶时进行砌筑。污水检查井流槽的高度与管顶齐平;雨水检查井流槽的高度为管径的1/2。当采用砖砌时,表面用1:2水泥砂浆分层压实抹
15、光,流槽须与上下游管道接顺;2.4.7抹面、勾缝技术要求砌筑检查井、井室的内壁用原浆勾缝,内壁抹面分层压实,外壁用砂浆搓缝严密。其抹面、勾缝、座浆、抹三角等均采用槽1:2水泥砂浆,抹面、勾缝用水泥砂浆的砂子过筛。2.4.7.1当有地下水时,井外壁抹面,其高度抹到地下水位以上500mm。2.4.7.2抹面厚度20mm。抹面时用水泥板槎平,待水泥砂浆初凝后及时抹光、养护。2.4.7.3勾缝采用平缝,要求勾缝砂浆塞入灰缝中,压实拉平深浅一致,横竖缝交接处应平整。2.4.7.4砖砌检查井施工时的注意事项:雨天砌井,在检查井坑开挖后,井身要一次砌起。必要时在井室底部预留进水孔,在填土前砌堵严实。检查井砌
16、筑部分砌好和砂浆达到规定强度后,即进行砖砌检查井的砌筑。检查井回填土前检查下列各项,并要符合下列要求:(1)井壁的勾缝抹面和防渗层符合质量要求;(2)井盖的高程要在5mm以内;(3)井壁同管道连接处须严密不得漏水。2.4.8回填与夯实 一般情况下,可以采用以下三类材料作为HDPE 管道的回填材料;第一类:5-40mm 的棱角石头,包括大量当地容易取得的材料,如珊瑚、碎矿渣、碎石及碎贝壳;第二类:最大直径40mm 的粗沙及砂砾,包括含有少量粉末的不同等级的沙子或砂砾,一般是粒状的且是不粘的,可以是湿的也可以是干的;第三类:优良的沙子与粘土砂砾,包括细沙,粘沙及粘土砂砾的混和物。 1). 防止槽内
17、积水造成管道漂浮,如有积水,应想办法排尽。 2). 对石方、土石混合地段的管槽回填时,应先装运粘土或砂土回填至管顶200-300mm,夯实后再回填其它杂土。 3). 回填必须从管两侧同时回填,回填一层夯实一层。 4). 管道试压前,一般情况下回填土不宜少于500mm。 5). 管道试压后的大面积回填,宜在管道内充满水的情况下进行,管道敷设后不宜长时间处于空管状态。 管材安装及回填完毕后,要对管道沿线设置醒目的警告标志,防止后续工程对管线开挖破坏。 钢筋混凝土管施工1工艺流程安管人工修整沟槽开挖砼垫层回填砌井接口2沟槽土石方开挖2.1确定好的开挖边线,采用人工配合履带挖机挖槽土,沟槽土方弃于沟槽
18、一侧1m以外,堆土高度不高于1.5m,弃方采用自卸汽车及时运走。开挖时控制好标高,严格按施工要求放坡,距槽底2030cm以内的土方层采用人工开挖,以免超挖和扰动槽底面。基槽在开挖前应用石灰撒出开挖的上口边边线,开挖的深度应用水平仪在现场边挖边测边用人工清理来控制;挖机开挖基坑应配备汽车,将挖出的土方及时用汽车运走。开挖的基坑槽应严格控制好断面尺寸使其与管身砼断面尺寸一致以免台背回填,挖机配合人工以避免超挖和少挖,开挖应将洞口的土方一起开挖接顺,避免二次调用机械。基坑检查基坑挖完后,须进行几何位置和标高检查和承载力的检查,承载力应不小于设计或规范的要求,如承载力达不到设计或规范要求,应根据监理工
19、程师的指示进行加强处理。用于垫层的砂砾级配应符合规范的要求,回填避免挤压位移。(2)施工顺序:施工准备(现场调查,测量放样)开挖沟槽砼基座管节安装接缝处理井洞口工程2.2施工时防止坍塌,如遇土质较差或地下水位高时,设置支撑,同时槽内采取排水沟和集水井法等措施抽排水,沟槽地基承载力要求满足设计规定,承载力不足时进行基础处理。2.3管座砼及下管2.4在沟槽底部每5m打一样桩,测量基标高,控制好基面,砂砾垫层须用振动夯实机夯实,人工拍平,运输过程中避免碰撞管道面出现裂纹。应从下游开始装,使接头面向上游2.4.1下管采用人工将管道吊入槽内,依据坡度线及中心线,将管子中心及标高调校就位,并用砼块固定好。
20、将管子与管座砼块接触的部位用等强度的砂浆填满、捣实,再浇捣砼并进行养护。安放予制管座砼块。下管时要注意以下几点:(1)下管时,避免沟壁坍塌。(2)设有专人指挥下管。(3)管子绑扎找好重心,平吊轻放,速度均匀。(4)管节下入沟槽时,不得碰撞沟槽壁支撑及槽内管道 2.4.2排水管接口采用钢丝网水泥砂浆接口,管内应保持整洁,清扫干净3.砌井3.1准备工作(1)清理基础表面复核尺寸位置和标高是否符合设计要求;(2)按设计要求选用合格机砖,并将砖湿润,但浇水要适量,否则会使墙面不清洁,灰缝不整;(3)准备砂浆,按照设计给定的砂浆配合比配料,拌制。控制好时间,使砂浆拌合均匀,做到随拌随用。3.2井砌筑技术
21、要点(1)在井坑放出检查井中心位置线,浇筑井底砼基础,按检查井半径摆出井壁砖墙位置;(2)在井基础面上,先铺砂浆后再砌砖,采用全丁24墙砌筑。采用内缝小外缝大的摆砖方法,外灰缝塞碎砖,以减少砂浆用量。每层砖上下皮竖灰缝应错开。随砌筑随检查弧形尺寸;(3)排水管管口伸入井室30mm,管顶砌砖圈加固,以减少管顶压力,拱圈高为250mm;(4)砖砌圆形检查井时,随砌随检测检查井直径尺寸。(5)排水检查井内的流槽,在井壁砌到管顶时进行砌筑。污水检查井流槽的高度与管顶齐平;雨水检查井流槽的高度为管径的1/2。当采用砖砌时,表面用1:2水泥砂浆分层压实抹光,流槽须与上下游管道接顺;3.3抹面、勾缝技术要求
22、砌筑检查井、井室的内壁用原浆勾缝,内壁抹面分层压实,外壁用砂浆搓缝严密。其抹面、勾缝、座浆、抹三角等均采用槽1:2水泥砂浆,抹面、勾缝用水泥砂浆的砂子过筛。3.4当有地下水时,井外壁抹面,其高度抹到地下水位以上500mm。3.5抹面厚度20mm。抹面时用水泥板槎平,待水泥砂浆初凝后及时抹光、养护。3.6勾缝采用平缝,要求勾缝砂浆塞入灰缝中,压实拉平深浅一致,横竖缝交接处应平整。3.7砖砌检查井施工时的注意事项:雨天砌井,在检查井坑开挖后,井身要一次砌起。必要时在井室底部预留进水孔,在填土前砌堵严实。检查井砌筑部分砌好和砂浆达到规定强度后,即进行砖砌检查井的砌筑。检查井回填土前检查下列各项,并要
23、符合下列要求:(1)井壁的勾缝抹面和防渗层符合质量要求;(2)井盖的高程要在5mm以内;(3)井壁同管道连接处须严密不得漏水。3.8沟槽回填2.4.7.1在钢筋砼管道的现浇砼基础强度、砼护座接口,抹带水泥砂浆强度不小于5N/mm2时,即进行沟槽砂砾及土方回填。管道项至设计路床标高全部回填砂砾石,用振动夯实机每15cm分层夯实,其各部位密实度须达到设计要求。2.4.7.2支管回填写土采用机械还土,按分层15cm厚要求,每一层采用人工摊平,采用人工夯实和振动夯实两种方法,填土夯实控制好土的含水量,在最佳含量时夯实,密实度须达到95以上,每层须实验测定合格后,方可进行下层土方填筑施工。2.4.7.3
24、施工中要注意以下几点:(1)采用砂砾素土回填时不得含有机物。(2)管道两侧和管顶以上50cm范围内不得回填大于50mm的砖、石等物,对称均匀分层回填,两侧高差不得超过30cm,以防止管道位移。填土时均匀地运土入槽,不得集中推入。2.4.8管井完成后,必须按规范要求进行闭水试验,达标后方可进行回填。回填前应清理管道内的垃圾和排干积水,并做好维护工作,保证下水道交验时畅通。2.5道路施工水泥稳定砂砾施工2.5.1配合比设计:试验室进行理论配合比设计,然后根据施工料场各集料含水量调整理论配合比,初步确定施工配合比;2.5.2进行试验路段施工,收集松铺系数、压路机碾压遍数等数据,编写试验路段施工总结报
25、监理工程师审定,并将各种技术参数汇编成作业指导书,作为后续施工的指导数据。2.5.3施工方案2.5.3.1施工工艺:水泥稳定砂砾基层施工工艺框图准备下承层拟定施工方案报请批准原材料检验及混合料配合比设计铺筑试验段摊铺混合料材料运送到位碾压现场拌和接缝处理填交交工报告、报请工程验收检测压实度保湿养生不小于7天交工验收取样试验施工放样表面拉毛、洒水湿润2.5.3.2施工方法2.5.3.2.1测量放样用全站仪将路线中、边桩放出,中桩按每10m一个布设,各变坡点、平曲线要素点加密中桩,并在铺筑区域设立加桩,测定标高,据试验路段所得松铺系数,计算实际填筑高度,挂线施工。2.5.3.2.2搅拌水泥稳定砂砾
26、采用稳定砂砾厂拌设备搅拌,配备自动计量的配料机送料,用装载机将集料送入配料机。作业时应随时注意以下事项:检查各材料输送系统是否工作正常,材料用量是否准确;机械的搅拌系统是否有损坏,混合料的均匀性是否一致;原材料的含水量、级配是否发生变化,如有变化,需立即进行调整配合比;按规定的频率对混合料进行抽检,检查其含水量、颗粒级配、强度,如有偏差,应立即调整;2.5.3.2.3运输:采用砼运输车运;2.5.3.2.4摊铺、平整铺筑前,清理底基层上的杂物,碾压一遍后洒水湿润根据松铺系数和每一车所运混合料量的多少,由有经验的施工员指挥卸车,控制混合料均匀地卸料在施工区域,卸料后立即用推土机初平,并按设计形成
27、路拱。初平按测量人员所挂标高控制线控制,检验松铺厚度是否符合要求,并随时进行调整。多余的混合料往前推,欠料的地方用人工补充。然后用平地机精平,检测标高合格后用压路机慢速静力初压一遍,以暴露潜在的不平整,再检测标高后用人工配合平地机进行精确平整和整型。2.5.3.2.5碾压分层碾压,经过整平和整型,使基层达到要求的路拱和纵坡,在全宽全厚的范围内将混合料均匀的压实,采用18t以上光轮振动碾进行复压,轮迹重叠1/31/2,速度控制在2km/h左右。复压完毕,选择小吨位压路机进行终压,以消除表面裂纹和轮迹,并保证密实。终压速度在4km/h左右。碾压施工时应注意以下事项:压路机工作时注意匀速行驶,不能急
28、起急停,停车时应停振减速,亦不能在新铺基层上急速转弯、掉头;混合料从出搅拌机至碾压完毕,最长时间不应超过2小时,并保证表面无轮迹,碾压遍数和方法由试验段来确定。要有测量员盯在现场,不断检测摊铺和碾压后的标高(左中右)及时调整施工中的偏差。挖除大料窝点及含水量超限点,并换填合格材料。用拌和好水泥砂砾对表面偏粗的部位进行精心修补。由于摊铺停顿和碾压推移产生的拥包、拥坎,用铁夯夯除、整平。对碾压过程中,如因气温高或风大,基层表面混合料失水后出现“白眼”现象时,应立即启动压路机的自动喷水装置,用潮湿的轮轴将“白眼”润湿,严禁用人工或洒水车洒水,以防冲走顶面水泥浆。用三米直尺逐段丈量平整度,发现异常,马
29、上处理。快速检测压实度,压实不足尽快补压。压实度控制一定要留有余地,尽量多压12遍,自检时压实度应按提高一个百分点掌握。2.5.3.2.6检验:首先表面应均匀无松散等现象,各项质量指标应满足标准要求,它不仅影响对该层的质量评定,同时也会对沥青砼表面层的质量和经济效益产生较大的影响。压实度不合格的应返工处理。平整度指标必须在做沥青透层之前,会同监理逐段进行测试。2.5.3.2.7接缝处理(1)车行道下每隔100m左右设置一道伸缩缝,缝宽2cm,采用沥青浸制木板填缝,并以缝为中心,铺设2m宽土工布。(2)摊铺混合料时,如因故中断时间超过2小时,则设置横向接缝,将摊铺段末未经压实的混合料铲除,并将已
30、碾压密实且高程和平整度符合要求的末端挖成与路中心线垂直并垂直向下的断面,并按伸缩缝要求进接缝处理,然后再摊铺新的混合料。(3)两段作业衔接处第一段留下58米不进行碾压,第二段施工时,将前段留下未压部分与第二段一起碾压;如果接缝处间隔时间过长,则采用台阶搭接法施工处理。局部难以碾压密实的地方用打夯机夯实。2.5.3.2.8养生养生是水泥稳定砂砾非常重要的一道工序,它直接影响结构层的成型和表观质量,设专人和专门设备进行养生。洒水养生不少于7天,且必须经常保持结构层表面湿润。2.5.3.2.9施工要点(1)施工时应根据原材料的含水量的变化而及时调整施工配合比,严格控制混合料的用水量,并保证摊铺时混合
31、料的含水量大于最佳含水量,以补偿摊铺碾压过程中的水分损失。(2)加强混合料均匀性控制,确保混合料的水泥剂量不超出波动范围。(3)碾压过程中,水泥稳定土的表面应始终保持湿润,如蒸发过快,则及时补洒少量的水,但严禁洒水碾压。碾压过程中,如有“弹簧”、松散、起皮等现象,及时翻开重新拌和(加适量的水泥)使其达到质量要求。(4)严格控制布料间距,保证供料连续。(5)工地气温低于5时,不进行施工。雨季施工,应特别注意天气变化,勿使水泥和混合料受雨淋。降雨时立即停止施工,但已摊铺的混合料尽快碾压密实,并立即覆盖薄膜。(6)施工接缝平整、稳定。2.5.3.2.10质量保证措施(1)施工员如实及时做好施工日记,
32、记录开停工时间、起始桩呈及施工过程中发现的问题等,质检员作好质量记录。(2)按规定要求作好各项试验和检测工作。按规定要求检测原材料,据原材料变化及时调整混合料的配合比。水泥稳定砂砾混合烊在施工现场每天取样一次,或按技术规定取样,检查混合料的含水量、水泥含量和无侧限抗压强度。在已完成的基层上按规定进行压实度试验,发现不合格产品立即采取措施,直至停工。施工质检人员按规范要求进行跟踪检测平整度、纵断面高程、宽度、横坡、中线平面偏位等。对检测不合格的项目及时采取措施进行处理,直到满足规范要求。 2.5.4试验室建设 现场建立工地试验室,试验室配备设备见表,所有实验设备经计量监督部门和监理部门鉴定合格后
33、方可使用,进场实验人员的资质和实验设备需报监理工程师认可方可使用。2.5.5 备料根据施工图纸确定各工序需要的材料规格和数量向业主提供材料供应计划,所有材料经检验合格后方可进场。 2.5.6 混合料配合比试验 2.5.6.1级配砂砾稳定土混合料组成设计 混合料的组成设计应按照公路路面基层施工技术规范(JTJ0342000)第5章有关规定办理。 级配砂砾混合料的设计应考虑气候,水文条件等因素,通过试验选取最适宜于稳定的砂砾级配最佳含水量。 施工前,应取有代表性的样品按规范要求对原材料进行试验。 2.5.6.2 水泥稳定砂砾混合料组成设计 20cm(30cm)厚4%(5)水泥稳定砂砾基层,其混合料
34、组成设计应符合公路中面基层施工技术规范(JTJ0342000)的有关规定。有关材料、最佳含水量、最优水泥剂量还应满足公路工程无机结合特稳定构料试验规程(JTJ05794)及招标文件中的技术规范规定要求,相关资料在浇筑前28天提交监理工程师审核批复。 2.5.7 实验路段的摊铺 在试验路开始至少14天之前,我们将包括使用的原材料和混合料组成设计,以及拌合、摊铺、碾压机械一览表和施工组织、工艺流程计划、施工工艺操作、试验方案及试验计划等详细书面说明报请监理工程师审批。 试验路长度50一100米,试验段施工前,将根据规范的要求对材料和混合料进行取样和试验,只有材料检测合格,混合料配合比设计结果经审批
35、后方可用于试验路段施工。 试验路段试验方案包括采用不同设备类型及技术,用不同的铺筑方法,施工工序和施工工艺,以检验承包人所采用的设备能否满足备料,拌和、铺筑的效率以及施工方法和施工组织的可靠性。 试验路铺筑前分为试拌和试铺两个阶段,根据施工机械相匹配的原则,确定合理的施工机械,机械数量及组合方式,通过试拌确定拌和机械上料速度,拌和数量与时间等,通过试铺确定材料的松铺系数、摊铺方法与操作工艺、压碾工艺。 通过试验路试铺,确定底基层、基层铺筑施工工艺,检验施工机具,完成对底层水泥稳定砂砾、基层水泥稳定砂砾建立施工,质量控制制度,使技术人员及操作人员熟练掌握加铺层铺筑施工工艺,试验路施工工艺按砼铺筑
36、施工工艺的规定进行,如经检验合格,可作为主体工程施工的依据。 试验路报告与工艺标准 试验路铺筑并检测完毕后,我们将马上提出试验路施工总结及加铺层施工工艺(改进部分)报请监理工师批准,试验路段确定的底基层,基层的压定方法,压实机械类型,工序、压定系数,碾压遍数,压实厚度工艺流程等均作为今后施工现场控制的依据。 试验路质量经监理工程师认可后,即可作为主体工程组成部分,并按合同规定的项目进行计量支付,任何不合格部分均将挖除、返工。2.5.8底基层的施工搅拌设备及布置位置应在拌和前提交监理工程师审批后方可安装检修、调试,使混合料颗粒组成,含水量达到要求。路床表面摊铺前应洒水湿润,扑经监理工程师审批。摊
37、铺时混合料含水量略大于最佳含水量。经摊铺成型的混合料应即在全宽范围压实,并在当日内完成碾压。一个路段完成之后,应按批准的方法做压实度试验,未达要求时应重型碾压,直到合格。养生时间不少于7天,期间应封闭交通。除洒水车外禁止车辆通行。2.5.9基层的施工所用材料应符合部颁规范及本投标书规定的要求。铺筑前应对底基层检查,清扫、洒水、整型、压实等。基层表面须经仔细整平、整型和压实,我们将按试验路段所确认的压实工艺,在全范围内均匀压实至重型击实最大密度96以上,基层横断面要符合设计要求。严禁压路机在完成碾压路段上调头和紧急刹车。两段作业衔接处,第一段留58m不进行碾压,第二段施工时,将前段留下未压部分与
38、第二段一起碾压。特别注意基层整修的时机。碾压完成后应立即进行养生,养生不少于7天,养生期间禁止重型车辆通过。2.6改性沥青混凝土施工方法1、施工准备工作(1)沥青混凝土所用粗细集料、填料以及沥青均应符合合同技术规范要求,并至少在工程开始前一个月将推荐混合料配合比包括:矿料级配、沥青含量、稳定度(包括残留稳定度)、饱和度、流值、马歇尔试件的密度与空隙率等的详细说明,报请监理工程师批准。(2)沥青混合料拌合设备,运输设备以及摊铺设备均应符合合同技术规范要求。(3)路缘石、路沟、检查井和其他结构物的接触面上应均匀地涂上一薄层沥青。(4)要检查两侧路缘石完好情况,位置高程不符要求应纠正,如有扰动或损坏
39、须及时更换,尤其要注意背面夯实情况,保证在摊铺碾压时,不被挤压、移动。(5)施工测量放样:恢复中线:在直线每10m设一钢筋桩,平曲线每5m设一桩,桩的位置在中央隔离带所摊铺结构层的宽度外20cm处。水平测量:对设立好的钢筋桩进行水平测量,并标出摊铺层的设计标高,挂好钢筋,作为摊铺机的自动找平基线。(6)沥青材料的准备,沥青材料应先加热,避免局部热过头,并保证按均匀温度把沥青材料源源不断地从贮料罐送到拌合设备内,不应使用正在起泡或加热超过160的沥青胶结料。(7)集料准备,集料应加热到不超过170,集料在送进拌和设备时的含水量不应超过1,烘干用的火焰应调节适当,以免烤坏和熏黑集料,干燥滚筒拌合设
40、备出料时混合料含水量不应超过0.5%。 2、拌和及其运输(1)拌和采用德国进口型号为LINT型沥青拌合设备(150t/h)集中拌合。集料和沥青材料按工地配合比公式规定的用量测定和送进拌和,送入拌合设备里的集料温度应符合规范规定,在拌合设备内及出厂的混合料的温度,应不超过160。把规定数量的集料和沥青材料送入拌合设备后,须把这两种材料充分拌和直至所有集料颗粒全部裹覆沥青结合料为度,沥青材料也完全分布到整个混合料中。拌和厂拌和的沥青混合料应均匀一致、无花白料、无结团块。拌好的热拌沥青混合料不立即铺筑时,可放入保温的成品储料仓储存,存储时间不得超过72h,贮料仓无保温设备时,允许的储料时间应以符合摊
41、铺温度要求为准。拌和生产出沥青混合料,应符合批准的工地配合比的要求,并应在目标值的容许偏差范围内,集料目标值的偏差应符合合同技术规范要求。 (2)沥青混合料运输 沥青混合料的运输采用15t的自卸车运输,从拌合设备向自卸车放料时,为减少粗细集料的离析现象,每卸一斗混合料挪动一下汽车位置,运料时,自卸车用篷布覆盖。 3、摊铺及碾压(1)摊铺a、混合料使用徐州产型号为LTU125型自动找平沥青摊铺机(最大摊铺宽度12.5m),进行全宽度摊铺和刮平。摊铺机自动找平时,采用所摊铺层的高程靠金属边桩挂钢丝所形成的参考线控制,横坡靠横坡控制器来控制,精度在0.1%范围。b、摊铺时,沥青混合料必须缓慢、均匀、连续不间断地摊铺。不得随意变换速度或中途停顿。摊铺机螺旋送料器中的混合料的高度保持不低于送料器高度的23。并保证在摊铺机全宽度断面上不发生离析。c、混合料的摊铺用国产摊铺机进行,以参考线控制铺筑层标高。d、上下两层之间的横向接缝应错开50cm以上。e、在机械不能摊铺及整修的地方,在征得监理工程师同意后可用人工摊铺和整修。f、在施工安排时,当气温低于10时不安排沥青混合料摊铺作业。(2)碾压a、一旦沥青混合料摊铺整平,并对不规则的表面修整后,立即对其进行全面均匀的压实。b、初压在混合料摊铺后较高温度下进行,沥青
链接地址:https://www.31doc.com/p-2067875.html