1、Project Management 3. Project Management Plans,Week 3,Project management plans,Why What How When Who,Why What How When Who,Why is this project happening? Why now? Why us?,Why What How When Who,What solution needs to be put in place to achieve the goals? What work needs to happen to build the solutio
2、n?,Why What How When Who,How do we get this solution in place? How do we know when were done?,Why What How When Who,When do work activities happen? What do we need to do first? Whats last?,Why What How When Who,Who do we need to deliver this project successfully?,And what will it cost?,$,Course obje
3、ctives Implement IT project planning and selection techniques Appreciate the importance of project portfolio management,The project management plan Benefits of planning What to consider in your plan Guidelines Reviewing a plan,The project management plan Benefits of planning What to consider in your
4、 plan Guidelines Reviewing a plan,Plans are useless. Planning is indispensible Dwight Eisenhower,The project management plan Benefits of planning What to consider in your plan Guidelines Reviewing a plan,http:/ plan?,Why plan?,http:/ Plan,The Plan,The Plan,The Plan,The Plan,The Plan,The Plan,Changes
5、 once you start,http:/ Plan,The Plan,The Plan,The Plan,The Plan,The Plan,The Plan,Changes once you start,Guides you activities,http:/ Plan,The Plan,The Plan,The Plan,The Plan,The Plan,The Plan,Changes once you start,Guides you activities,Makes you think ahead,http:/ Plan,The Plan,The Plan,The Plan,T
6、he Plan,The Plan,The Plan,Changes once you start,Guides you activities,Makes you think ahead,Helps you work out who you need to hire,http:/ Plan,The Plan,The Plan,The Plan,The Plan,The Plan,The Plan,Changes once you start,Guides you activities,Makes you think ahead,Helps you work out who you need to
7、 hire,Works out the timeline and budget,http:/ Plan,The Plan,The Plan,The Plan,The Plan,The Plan,The Plan,Changes once you start,Guides you activities,Makes you think ahead,Helps you work out who you need to hire,Helps manage expectations,Works out the timeline and budget,http:/ Plan,The Plan,The Pl
8、an,The Plan,The Plan,The Plan,The Plan,Changes once you start,Guides you activities,Makes you think ahead,Helps you work out who you need to hire,Helps manage expectations,Works out the timeline and budget,Helps understand the effects of changes,http:/ Plan,The Plan,The Plan,The Plan,The Plan,The Pl
9、an,The Plan,Changes once you start,Guides you activities,Makes you think ahead,Helps you work out who you need to hire,Helps manage expectations,Makes sure you are doing the right thing,Works out the timeline and budget,Helps understand the effects of changes,The project management plan Benefits of
10、planning What to consider in your plan Guidelines Reviewing a plan,?,Who will read it? What do they need to know? Do they come in cold?,What is your project going to deliver?,Scope,The work to be done,=,The target product,Hunt, B. et al. (2003). Project charter. Retrieved January 23, 2006 from http:
11、/ (partial),Hunt, B. et al. (2003). Project scope statement. Retrieved January 23, 2006 from http:/ (partial),What is your project going to deliver?,Definition,The work to be done,=?=,The target product,What is your project going to deliver?,Change control,The work to be done,=?=,The target product,
12、What is your project going to deliver?,Value?,The work to be done,=?=,The target product,The WBS,The right way,The wrong way,Focus on deliverables,Focus on processes,Align to value,Align to process stages,Why?,Why not?,Figure 5.2 Sample hierarchical WBS organized by phase (Schwalbe, 2006, p176),The
13、wrong way?,Note the Layers,Table 5.3 Sample tabular WBS (Schwalbe, 2006, p176),1.0 Concept 1.1 Evaluate current systems 1.2 Define requirements 1.2.1 Define user requirements 1.2.2 Define content requirements 1.2.3 Define system requirements 1.2.4 Define server owner requirements 1.3 Define specific
14、 functionality 1.4 Define risks and risk management approach 1.5 Develop project plan 1.6 Brief Web development team 2.0 Web Site Design 3.0 Web Site Development 4.0 Roll Out 5.0 Support,http:/.au/images?hl=en&q=wbs&btnG=Search+Images&gbv=2,Document your assumptions,Very little knowledge,Complete kn
15、owledge,Degree of knowledge over time,OBS,Figure 9.2 Sample Project Organizational Chart (Schwalbe, 2006, p358),Task 1,Task 2,Task 3,Task 4,Task 5,Task 6,Person 1,Person 2,Person 3,Person 4,http:/ 9.6 Sample Resource Histogram (Schwalbe, 2006, p362),tools,rasci (aka raci),ram,http:/ 1,Task 2,Task 3,
16、Task 4,Task 5,Task 6,Person 1,Person 2,Person 3,Person 4,R,R,R,R,R,R,Figure 9.4 Sample Responsibility Assignment Matrix (RAM) (Schwalbe, 2006, p360),OBS: Organizational Breakdown Structure WBS: Work Breakdown Structure,One and only one person can be accountable. Multiple people can be responsible an
17、d certainly others can be informed and consulted. Source: Glen B Alleman, (2007) Responsibility Assignment Matrix, Herding Cats http:/ retreived 2/8/08,One and only one person can be accountable. Multiple people can be responsible and certainly others can be informed and consulted. Source: Glen B Al
18、leman, (2007) Responsibility Assignment Matrix, Herding Cats http:/ retreived 2/8/08,Project organisations go farther than workers and work,Project Team structure,Project Sponsor,Project Manager Craig Brown,Working Group: Design focus OLA decisions and choices Formal review & validation of deliverab
19、les Business input and SME access,Steering Committee: Governance focus Approval of project strategy & plans Endorsement of key OLA decisions Final approval of the OLA Business case and Solution Design Removal of major roadblocks & prioritisation,Analysts,Testers,Designer,Change consultants,Working G
20、roup Marketing Product Management Legal Finance Sales Customer Service,Steering Committee Head of Marketing and Sales Head of Product Management Head of Customer Service Head of Finance,Developers,Remember this?,You might break down the work by phases,Why?,http:/ now you know what needs to be done,S
21、o now you know what needs to be done,and who is going to do it.,So now you know what needs to be done,and who is going to do it.,But what about when?,Schedule,http:/ 3.3 Sample network diagram (partial) (Schwalbe, 2006, p211),Table 3.10 Sample milestone report (partial) (Schwalbe, 2006, p100),Figure
22、 3.3 Sample Gantt chart (partial) (Schwalbe, 2006, p97),http:/ Resource plan Schedule,Why What How When Who,And what will it cost?,$,Constructing a budget is easy Sticking to it is hard.,How will you Monitor and Control the project? Who needs to know?,Galloway, M. (2004). Status report. Retrieved Ja
23、nuary 23, 2006 from http:/web.augsburg.edu/oie/mis376/documents/SR1.doc (partial),Risk management,Degree of knowledge over time,BetterP http:/ project management plan Benefits of planning What to consider in your plan Guidelines Reviewing a plan,Six-Step Proven Path for Schedule Development Rudi van den Berg, Pcubed, Inc. http:/ project management plan Benefits of planning What to consider in your plan Guidelines Reviewing a plan,BetterP,