1、BRITISH STANDARD BS EN 62337:2007 Commissioning of electrical, instrumentation and control systems in the process industry Specific phases and milestones The European Standard EN 62337:2007 has the status of a British Standard ICS 25.040.01 ? Licensed Copy: London South Bank University, London South
2、 Bank University, Wed May 16 03:52:35 GMT+00:00 2007, Uncontrolled Copy, (c) BSI BS EN 62337:2007 This British Standard was published under the authority of the Standards Policy and Strategy Committee on 31 May 2007 BSI 2007 ISBN 978 0 580 50650 5 National foreword This British Standard was publishe
3、d by BSI. It is the UK implementation of EN 62337:2007. It is identical with IEC 62337:2006. The UK participation in its preparation was entrusted to Technical Committee GEL/65, Measurement and control. A list of organizations represented on this committee can be obtained on request to its secretary
4、. This publication does not purport to include all the necessary provisions of a contract. Users are responsible for its correct application. Compliance with a British Standard cannot confer immunity from legal obligations. Amendments issued since publication Amd. No. DateComments Licensed Copy: Lon
5、don South Bank University, London South Bank University, Wed May 16 03:52:35 GMT+00:00 2007, Uncontrolled Copy, (c) BSI EUROPEAN STANDARD EN 62337 NORME EUROPENNE EUROPISCHE NORM March 2007 CENELEC European Committee for Electrotechnical Standardization Comit Europen de Normalisation Electrotechniqu
6、e Europisches Komitee fr Elektrotechnische Normung Central Secretariat: rue de Stassart 35, B - 1050 Brussels 2007 CENELEC - All rights of exploitation in any form and by any means reserved worldwide for CENELEC members. Ref. No. EN 62337:2007 E ICS 25.040.01 English version Commissioning of electri
7、cal, instrumentation and control systems in the process industry - Specific phases and milestones (IEC 62337:2006) Mise en service des systmes lectriques de contrle/commande et dinstrumentation dans les industries de processus - Phases spcifiques et tapes (CEI 62337:2006) Inbetriebnahme elektrischer
8、 und leittechnischer Systeme in der Prozessindustrie - Phasen und Meilensteine (IEC 62337:2006) This European Standard was approved by CENELEC on 2007-02-01. CENELEC members are bound to comply with the CEN/CENELEC Internal Regulations which stipulate the conditions for giving this European Standard
9、 the status of a national standard without any alteration. Up-to-date lists and bibliographical references concerning such national standards may be obtained on application to the Central Secretariat or to any CENELEC member. This European Standard exists in three official versions (English, French,
10、 German). A version in any other language made by translation under the responsibility of a CENELEC member into its own language and notified to the Central Secretariat has the same status as the official versions. CENELEC members are the national electrotechnical committees of Austria, Belgium, Bul
11、garia, Cyprus, the Czech Republic, Denmark, Estonia, Finland, France, Germany, Greece, Hungary, Iceland, Ireland, Italy, Latvia, Lithuania, Luxembourg, Malta, the Netherlands, Norway, Poland, Portugal, Romania, Slovakia, Slovenia, Spain, Sweden, Switzerland and the United Kingdom. Licensed Copy: Lon
12、don South Bank University, London South Bank University, Wed May 16 03:52:35 GMT+00:00 2007, Uncontrolled Copy, (c) BSI Foreword The text of document 65/384/FDIS, future edition 1 of IEC 62337, prepared by IEC TC 65, Industrial-process measurement and control, was submitted to the IEC-CENELEC parall
13、el vote and was approved by CENELEC as EN 62337 on 2007-02-01. The following dates were fixed: latest date by which the EN has to be implemented at national level by publication of an identical national standard or by endorsement (dop) 2007-11-01 latest date by which the national standards conflicti
14、ng with the EN have to be withdrawn (dow) 2010-02-01 _ Endorsement notice The text of the International Standard IEC 62337:2006 was approved by CENELEC as a European Standard without any modification. _ EN 62337:2007 2 Licensed Copy: London South Bank University, London South Bank University, Wed Ma
15、y 16 03:52:35 GMT+00:00 2007, Uncontrolled Copy, (c) BSI 3 EN 62337:2007 CONTENTS INTRODUCTION.4 1 Scope 5 2 Terms and definitions.5 3 General preparations before acceptance of plant.7 4 Completion of erection7 4.1 Mechanical checks and tests .7 4.2 Procedure .8 5 Precommissioning (mechanical comple
16、tion) 8 5.1 General.8 5.2 Procedure .8 6 Commissioning.9 6.1 General.9 6.2 Procedure .9 7 Performance test and acceptance of plant.10 7.1 General.10 7.2 Conditions for commencement of performance test.11 7.3 Execution of performance test11 7.4 Evaluation and report of performance test 12 Annex A (in
17、formative) List of documents to be used for the precommissioning and commissioning phase13 Annex B (informative) Description of precommissioning activities14 Annex C (informative) Mechanical completion certificate.25 Annex D (informative) Description of commissioning activities 26 Annex E (informati
18、ve ) Acceptance of plant certificate 28 Annex F (informative) Project-specific items .29 Licensed Copy: London South Bank University, London South Bank University, Wed May 16 03:52:35 GMT+00:00 2007, Uncontrolled Copy, (c) BSI EN 62337:2007 4 INTRODUCTION There is an increasing trend in the process
19、industry to award the construction of whole plants to contractors on a lump-sum turnkey or similar commercial basis. Experience has shown that both the process industry (hereinafter called “the owner”) and the contractor have long and expensive discussions to lay down unambiguously the scope of acti
20、vities to be taken by the contractor and the owner and their responsibilities to achieve the handover of the plant. This standard should lead to an improvement and acceleration of the negotiation phase and to a mutual understanding about the scope of activities of each party. For application in the
21、pharmaceutical or other highly specialized industries, additional guidelines (for example, Good Automated Manufacturing Practice (GAMP), definitions and stipulations should apply in accordance with existing standards, for example, for GMP Compliance 21 CFR (FDA) and the Standard Operating Procedure
22、of the European Medicines Agency (SOP/INSP/2003). Licensed Copy: London South Bank University, London South Bank University, Wed May 16 03:52:35 GMT+00:00 2007, Uncontrolled Copy, (c) BSI 5 EN 62337:2007 COMMISSIONING OF ELECTRICAL, INSTRUMENTATION AND CONTROL SYSTEMS IN THE PROCESS INDUSTRY SPECIFI
23、C PHASES AND MILESTONES 1 Scope This International Standard defines specific phases and milestones (see Figure 1) in the commissioning of electrical, instrumentation and control systems in the process industry. By way of example, it describes activities following the “completion-of-erection” milesto
24、ne of the project and prior to the “acceptance-of-the-plant” phase by the owner. Such activities need to be adapted for each type of process/plant concerned. NOTE This standard assumes that the “acceptance-of-the-plant” milestone will occur after the performance test. If there is a reduced scope, th
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- BS EN 62337 2007
链接地址:https://www.31doc.com/p-3749804.html